Variations during a build are likely to occur so accepting it’s a possibility upfront is a good thing.
You might want to make a change for the better (or remove certain work), the builder may recommend a change for the better or an unexpected situation may arise through no fault of anyone.
You need to draw on those good communication skills of yours and work through the variation to avoid any disputes.
Here’s what’s important:
1. You get a cost of the variation in writing BEFORE the work is carried out.
2. You check if the variation needs Council approval.
3. You understand the requirements of the variation e.g. description, materials, time to complete.
4. Both parties sign off on the variations before work is carried out.
Thinking about becoming an Owner Builder? Unlock your potential with key insights to make an informed decision. Gain the knowledge and confidence to start your journey with clarity and certainty ✅
Unlock your owner builder potential with our step-by-step guide. From design to permits, get the insights you need to plan and prepare for a smooth, successful build from day one 💪🏼
Confidently bring your owner builder dream to life with our expert guide. Crafted with two registered builders, this step-by-step resource covers each build stage, providing essential quality checks, trades, and materials to help you build with precision and confidence 🔨