SEQUENCE FOR INTERNAL FIT-OUT TRADE INSPECTION/ CERTIFICATION?
Electrical / plumbing / data / air-conditioning rough in prior to wall lining Electrician/Plumber
Ceiling and wall insulation Carpenter
Plasterboard sheet and setting and sand off Plasterer
Organise carpenter for fix out e.g. doors, skirting, architraves, door hardware Carpenter
Organise joinery to be installed e.g. kitchen Joiner
Waterproofing to wet areas Waterproofer Check if inspection is required (differs by state)
Tiling to wet area walls and floors Tiler
Electrician/Plumber/Air-conditioner to fit off (ensure goods are on site) Electrician/Plumber
Organise painter for inside and out Painter
Stormwater drains connected and inspected by Building Surveyor where applicable Plumber Inspection
Installation of shower screens and mirrors Specialised trade
Install carpet (if applicable) Carpet supplier
Blind installation Supplier
Install carpet Carpet supplier
Check, check and check all work done by trades! Owner Builder