SEQUENCE FOR THE CONCRETE SLAB TRADE INSPECTION/ CERTIFICATION?
Excavate perimeter footing Concreter
Install plumbing pipework under slab (drains, pipe, gas, waste) Licensed Plumber
Install conduit for future services where needed e.g. electrical or data cables and for power that can't be reached through frame main e.g. island bench Licensed Electrician
Termite treatment including of services that will penetrate slab Termite specialist
Boxing up and preparation of slab (prior to pour) Concreter
Coordinate critical inspection with Building Surveyor to be carried out prior to pour Building Surveyor Critical inspection
Pour slab Concreter
Provide facility to contain rubbish (rules by differ by state, check local rules) Owner Builder